Proserpine Main Street Drainage Upgrade

As part of Council’s Capital Works Program for 2016/17, Council’s Works Department will be upgrading the stormwater drainage system (situated within the parking areas) along the Main Street of Proserpine between the intersections of Hinschen Street & Chapman Street.

Works will commence on Monday, 22 August 2016 and it is anticipated that this work will extend up to November 2016. The project crew will work five days a week from Monday to Friday between the hours of 6:30am to 5:00pm as required.

The works will include installation of reinforced concrete pipes, box culverts, kerb & channel and associated pavement reconstruction.

Whilst Council will endeavor to keep disruptions to a minimum, we regret that traffic delays will occur due to partial and full road closures along this section of the street at times in order to undertake the works. However, accesses to the properties and business premises will be maintained at all times during this work.

schedule of works

Whitsunday Regional Council's Works Department has planned to undertake this project in six stages as listed below.

Please note: these are estimated timeframes only and are subject to change in the event  of adverse weather conditions and delivery of materials.
  
 

stage anticipated timeframe
Stage 1 - Hinschen Street to Mill Street
Right hand side (Sugar Mill side)
Parking bays will be closed on both sides
No lane closures

COMPLETED


22 August - 14 September                                 
Stage 2 - Hinschen Street to Mill Street
Left hand side (Entertainment Centre side)
LHS parking bays will be closed
No lane closures

COMPLETED


22 August - 14 September
Stage 3 - Dobbins Lane to Chapman Street
LHS excluding the roundabout
One lane operation will be maintained at all times
LHS parking bays will be closed

24 October - 7 November
Stage 4  - Dobbins Lane to Chapman Street
RHS excluding the roundabout
One lane operation will be maintained at all times
RHS parking bays will be closed

 3 October - 26 October
Stage 5 - Roundabout at Chapman Street and Main Street
 LHS - approaches to Main Street, from both sides of Chapman Street will be restricted
To minimise disruption, works will be undertaken on weekends

 On hold
Stage 6 - Roundabout at Chapman Street and Main Street
 RHS - approaches to Main Street, from both sides of Chapman Street will be restricted
To minimise disruption, works will be undertaken on weekends

 3 October - 26 October
Stage 7 - Final trimming and asphalt works for the entire length of the works. 12 November - 15 November

 
Council apologies for any inconvenience and seek your co-operation during this important upgrade.

If you have any queries regarding this work please contact Council’s Depot Administration on (07) 4945 0622.
  

  1. P  07 4945 0200
    Email  info@whitsundayrc.qld.gov.au

    CUSTOMER SERVICE CENTRES
    67 Herbert Street, Bowen
    Cnr. Stanley and Conway Streets, Collinsville
    83-85 Main Street, Proserpine
  1. LINKS

    My Dashboard   |   Privacy   |   Disclaimer   |   Accessibility   |   Site Map


    Powered by CivicPlus from ICON Software
  1. FOLLOW US
    Facebookin

    © Copyright Whitsunday Council 2014